Hydroseeding for Erosion and Sediment Control on slope
Coconut Cloth vs. Hydroseeding

A local company looked to revegetate a pipeline right-of-way. Their original plan was to cover approximately 1 HA area with coconut cloth.

Coconut Cloth Method (approx. 1 HA):
  • Provides erosion control on slopes
  • Used on previous jobs
  • Estimated 1 week installation time with 4 man crew
Costs Include:
  • Industrial grade coconut cloth per square meter
  • Installation (labour, stapling)
Coconut Cloth vs Hydroseeding in 1 Hectare
Before committing to coconut cloth, this company consulted Pineview to review the plan prior to starting the project.


Hydroseeding Method (approx. 1 HA):
  • Developed an Erosion and Sediment Control Plan (ESCP)
  • Suggested hydroseeding as an alternative w/ high grade mulch
  • Installation in 2 days with 4 man crew
Costs Include:
  • Materials & Installation per square meter
  • High Grade Mulch used on slopes
  • Seed, fertilizer, tackifier, transport, water, labour
  • Fixed price no matter installation time

You might also like

Pineview Vegetation Management Blog

02 May, 2024
Say NO to Sediment Runoff
04 Apr, 2024
Spring Hydroseeding & More!
01 Mar, 2024
Wildfires & Invasive Species Awareness
More Posts
Share by: